News24 | Eskom backtracks on pollution pledge, risking World Bank angst

1 week ago 9

Generators in the turbine hall of the Medupi coal-fired power station in Lephalale, Limpopo.

Generators in the turbine hall of the Medupi coal-fired power station in Lephalale, Limpopo.

Waldo Swiegers/Bloomberg via Getty Images


Eskom Holdings, the world’s biggest emitter of the toxin sulphur dioxide, presented a study that argues against the cost of installing equipment to limit emissions, risking a breach of a World Bank loan agreement and riling environmental activists.

The South African utility said the cost of retrofitting so-called wet flue-gas desulphurisation (FGD) units at its Medupi power plant would amount to R383 billion in installation and running costs. By comparison, an offset programme to supply local communities with clean cooking equipment to replace the use of coal would cost R5.1 billion, it said.

In 2010, Eskom borrowed $3.75 billion from the World Bank to complete the plant in South Africa — one of the world’s largest coal-fired power facilities — on condition that it install pollution-abatement equipment. In 2021, the utility said it had agreed with the lender to delay the installation to June 2027 from the original 2025 deadline.

“The monetised health-benefit value of the reduction in sulphur dioxide emissions is substantially less than the capital and operating expenditure for FGD,” Eskom said in the study released late on Tuesday. Health benefits are “orders of magnitude less than the cost of implementing wet FGD at Medupi,” it said.

The World Bank and Eskom didn’t immediately respond to queries. The study is now open for public comment.

Sulphur dioxide pollution causes respiratory illnesses and acid rain. Eskom has said that in addition to being expensive, the FGD equipment would increase water consumption, necessitate the use of large quantities of limestone, and produce additional carbon dioxide, a greenhouse gas.

“They’ve carefully excluded all significant population centres from the study,” Lauri Myllyvirta, lead analyst at the Helsinki-based Centre For Research on Energy and Clean Air, said by text message. “The benefit of FGD is grossly underestimated.”

Eskom said the suggested offset programme would produce significant benefits.

Clean cooking “delivers pronounced health benefits by reducing household air pollution,” Eskom said. “Estimated health benefits significantly exceed implementation costs by more than 30 times.”

Newsletter

Daily

SA Money Daily

The biggest business, economic and market news of the day.

Sign up

Read Entire Article
Progleton News @2023